Strategic Services · The Centre of Glengarra

Strategic expertise
where decisions matter.

Independent, multidisciplinary expertise applied where capital-project decisions have the greatest consequence.

Independent perspective. Deep delivery experience. Clear thinking.

Illustrative Project Intelligence
€350mInvestment
P80Schedule confidence
€11.4mForecast exposure
143Critical activities
3Decisions required

01 · Before Sanction

Build confidence before capital is committed.

We challenge scope, estimate, schedule and delivery strategy as one investment decision, not four separate conversations.

Illustrative: investment decision
Option A €218m 31 months Higher delivery exposure
Option B €196m 34 months Balanced
Option C €184m 39 months Lower delivery exposure
Scope maturity
Estimate confidence
Schedule confidence
Delivery risk
Recommended investment basis Option B: €196m, 34 months

02 · Investment Confidence

Know whether the forecast can be believed.

Integrated assurance across cost, schedule and risk: tested together, not signed off in isolation.

Illustrative: project assurance position
Schedule
P5018 Dec P8014 Feb
915 activities <20 days float
Cost
€296m Current EAC → €307m P80 exposure
Risk
12Material risks
3Critical decisions

03 · Independent Challenge

An objective view of where the project really stands.

A repeatable, rapidly deployable review method that looks underneath the reported position, not a repeat of it.

Illustrative: independent project diagnostic
Scope
Cost
Schedule
Risk
Governance
Delivery
12 findings · 4 material · 3 immediate decisions
Finding 07 of 12 Schedule

Current completion forecast does not adequately reflect commissioning interface risk.

Implication Mechanical completion and CQV are being sequenced as independent workstreams when they are not. The reported date assumes a handover that hasn’t been tested.

Potential impact6–10 weeks
Management actionRevalidate integrated MC/CQV sequence

04 · Structure & Control

Put the right decisions in the right place.

Governance is a decision architecture, not a layer of bureaucracy.

Illustrative: decision system
  1. 01 Information
  2. 02 Recommendation
  3. 03 Authority
  4. 04 Decision: 2 decisions >30 days
  5. 05 Action
7Decisions pending
€14.2mCapital exposed
The issue

The system stalls between authority and decision, not between recommendation and authority.

Satellite image of the Yukon River delta, Alaska, showing its branching channel network

05 · Recovery & Uplift

Turn insight into measurable improvement.

We identify where a project has drifted, then help turn that insight into action.

Illustrative: intervention waterfall
Base forecast €312m
Scope challenge −€8.4m
Procurement −€3.7m
Delivery strategy −€5.1m
Risk adjustment +€2.2m
Revised forecast €297m
Net opportunity €15m

06 · Recurring Proposition

Independent oversight that stays with the programme.

For major programmes and portfolios, Glengarra remains alongside leadership as capital continues to be deployed: as recurring oversight, periodic assurance at key decision points, or event-driven intervention when something changes.

Illustrative: capital portfolio

€941m under active review across four programmes.

Programme A €420m
Programme B €185m Gate: schedule confidence below threshold
Programme C €96m
Programme D €240m Review: cost trending against plan
2Interventions live
1Investment decision

Two of four programmes require intervention this quarter.

Management Intelligence

From project data to management decision.

Illustrative: management view Project Position: October
Cost €296.4m EAC ↑ €3.2m period movement
Schedule 92.8% actual 98.2% planned · −5.4% variance
Risk €18.6m P80 exposure ↑ €2.1m
Delivery 218 / 404 MC achieved Attention required
Three things leadership needs to know
01

Completion risk is increasingly concentrated in electrical termination and I/O testing.

02

32% of remaining activities now carry less than 20 days float.

03

Forecast cost increased €3.2m this period, primarily driven by piping and schedule assurance.

Strategy. Results.

It’s Our Nature.

Complex projects reward the ability to see both the detail and the whole: knowing when to go deeper, when to step back, and when enough is known to decide and move.

That’s where Glengarra is at its best.

Bring us the project before the answer is obvious.

Bring us an investment you’re shaping, a delivery strategy you want tested, or a project under pressure. We’d like to hear about the challenge.

International expertise on major capital projects.